Code No: A2503
Jawaharlal Nehru Technological University Hyderabad
M. Tech I-Semester Supplementary Examinations September-2009
SOFTWARE PROCESS AND PROJECT MANAGEMENT
(Software Engineering)
Time : 3 Hours Max. Marks: 60
Answer Any Five Questions
All Questions Carry Equal Marks

1.a) What are the six basic principles of software process change? Explain.
b) Briefly explain Assessment process in software process Assessment.

2. Write notes on configuration Management Process.

3.a) What are the benefits of SQA?
b) What are the responsibilities of SQA?
c) Write short notes on SQA reporting.

4.a) What are the basic objectives of software Inspections?
b) Write short notes on software tests.

5.a) What are the activities of risk management?
b) Write short notes on software life cycle models.

6. Write notes on project Tracking.

7.a) Briefly explain closure Analysis report.
b) Write short notes on modern process Transitions.

8. Explain briefly the following:
a) Quality Indicators
b) Issue Tracking
c) Reviews and Inspections.